SCOPE OF WORKS:
3rd July 2019: Works commence.
The works will include some major excavation by mechanical digger to source and replace the damaged pipes allowing greater egress for water should future flooding occur. Sadly, some plants covering the major blocked artery will have to be removed, but others will be re-instated to bring the garden back to its former glory. The works are expected to take 10 days with restorative works to follow shortly thereafter. Sadly during this work period there will be no access to residents.
Works update;
4th July 2019
Excavator works complete.
5th July 2019
Main pit installed.
8th July 2019
Two drainage pipes to side lane way installed.
24th July 2019
Drain covers final fix.
25th July 2019
Awaiting re-landscaping. Closed until further notice.
10th August 2019
Landscaping contractor confirmed. Garden works imminent.